Vimbanayi Project

Project Specifications

Location

Chipinge district, Manicaland Province (-21.027238 E, 32.198039 S)

Crops

Cash crops: chili pepper, tomatoes, maize and sugar beans

Completion Date

October 2025

Size

33ha

Scope

Project Challenges

The irrigation scheme faced myriad of challenges which include;

  • a 200mm dia AC pipe mainline which was not adequate to deliver the required flow rate to the irrigation area,
  • high susceptibility to climatic hazards such as floods, droughts and cyclones
  • leakages on the main pipeline from the pump station to the distribution chamber,
  • the pump station was entirely dependent on power supply from the national grid which experiences frequent power cuts,
  • high operational costs in the form of electricity tariffs.

The Forster Irrigation Solution

Forster irrigation provided the following to achieve climate proofing and revitalisation activities:

✓ Installation of 62kw solar field to power pumps and lessen the electricity bill

✓ Installation of an abstraction system in the Save river which taps water from both the surface and sub-surface flows

✓ Utilised the existing idle PVC pipe to increase the amount of water delivered to the reservoir tanks

✓ Installation of a night storage dam – 2 reservoirs to allow for storage of water and water abstraction to continue during periods of no irrigation

✓ Expansion of the irrigation area by 10ha in order to increase the sizes of the plot holdings for the farmers and supplying irrigation siphons

✓ Repairing the existing canals and sluice gates to reduce water losses

✓ Installation of a storm-water drainage system to collect excess runoff for safe disposal into the river

✓ Training of the IMC and beneficiaries on improved water management and irrigation scheduling