Mhondoro and Norton, Zimbabwe
Storage solution
25 June to 02 August 2026
The project encountered several operational and community-related challenges during implementation:
Forster Irrigation implemented direct technical and project management interventions to guarantee full operational success:
Filtration Engineering (Silt Mitigation): Installed 2-inch heavy-duty disc filters to trap fine silt particles before reaching the meters and valves, eliminating clogging and extending hardware lifespan.
Agile Task Sequencing: When community trenching slowed down at one site, technical crews dynamically pivoted to concurrent tasks (palisade fencing, solar light mounting, and storage tank erection) to prevent downtime.
Extended Crew Hours: To bridge the gap caused by low local labor turnout, Forster Irrigation deployed additional on-site technical personnel and extended working hours to maintain pipeline laying schedules.
Despite severe ground-water siltation and local labor shortages, Forster Irrigation successfully installed 13 km of reticulation infrastructure, 40,000L of storage, and secured pump stations across Mhondoro and Norton on schedule.
Contact us with your queries and we'll do our best to get your project flowing!